The $1 billion Infrastructure Acceleration Fund (IAF) invests in infrastructure that supports new housing developments in areas that face the biggest housing supply and affordability issues throughout New Zealand.
We were initially engaged by Buller District Council to provide conceptual engineering design, design report, schedule of quantities and engineers estimate to achieve IAF funding approval for a proposed growth area on the west side the Buller River. A team from Westport, Greymouth, Christchurch and Nelson successfully delivered the works under a strict time frame of just eight weeks.
We assessed existing and future demand for three waters services, lighting, roading, and utilities servicing. We coordinated specialist, lighting, power and transportation engineering subconsultants.
Subsequently, after the IAF funding was approved, we provided the detailed design for four separate IAF work streams – the Westport Wastewater Treatment Plant Inlet Works Upgrade (WWTP); Alma Road water main extension; wastewater servicing; and transportation and stormwater design, which included two intersection upgrades, a new 2-lane bridge at Lagoon Creek and a proposed shared pathway and crossings over State Highway 67.
Complex challenges due to the topography and elevation of the site were met through innovative solutions.
To ensure the Lagoon Creek bridge design was to the correct freeboard above Lagoon Creek in a 1-in-100-year flood, we completed a hydraulic stormwater model for the large contributing catchment of Gillow Dam. This was also used to inform flood hazard identification for the Westport Master Plan.
The $1 billion Infrastructure Acceleration Fund (IAF) invests in infrastructure that supports new housing developments in areas that face the biggest housing supply and affordability issues throughout New Zealand.
We were initially engaged by Buller District Council to provide conceptual engineering design, design report, schedule of quantities and engineers estimate to achieve IAF funding approval for a proposed growth area on the west side the Buller River. A team from Westport, Greymouth, Christchurch and Nelson successfully delivered the works under a strict time frame of just eight weeks.
We assessed existing and future demand for three waters services, lighting, roading, and utilities servicing. We coordinated specialist, lighting, power and transportation engineering subconsultants.
Subsequently, after the IAF funding was approved, we provided the detailed design for four separate IAF work streams – the Westport Wastewater Treatment Plant Inlet Works Upgrade (WWTP); Alma Road water main extension; wastewater servicing; and transportation and stormwater design, which included two intersection upgrades, a new 2-lane bridge at Lagoon Creek and a proposed shared pathway and crossings over State Highway 67.
Complex challenges due to the topography and elevation of the site were met through innovative solutions.
To ensure the Lagoon Creek bridge design was to the correct freeboard above Lagoon Creek in a 1-in-100-year flood, we completed a hydraulic stormwater model for the large contributing catchment of Gillow Dam. This was also used to inform flood hazard identification for the Westport Master Plan.